Tirana’s new boulevard: Abu Dhabi fund financed 27 mln euro, 6 mln euro for the underground parking
About 27 million euro is the amount made available for the construction of Tirana’s new boulevard, of which € 6m were the cost of the underground parking.
The Municipality of Tirana has been able finance this project through an Abu Dhabi fund loan with a total value of 48 million euro.
Part of this loan is also the project for rehabilitation of Tirana River with an amount of 20.5 million euro, including 2.5 million Euro for oversight and 4.5 million Euro as reserve fund.
This project consists in the construction of a boulevard 1.8 kilometers long and 70 meters wide, starting from the former Train Station to the bank of the Tirana River.
At the beginning of the boulevard there is a two-storey underground parking lot with a capacity of 321 parking spaces, 8 parking spaces for the disabled and an electric parking place.
Currently, about 50% of the total construction work for the new boulevard has been realized, with 300 lighting spots, 1100 trees and 7300 bushes.
SCAN
*Material i përgatitur nga portali SCAN. Ripublikimi mund të bëhet vetëm kundrejt citimit të autorësisë dhe burimit origjinal.